8 July 2018
Ministry of Electricity and Energy started construction work of 230 kV Hlaingtharyar-Kyaiklat Transmission Line (52.26) miles and 230/66/11 kV၊ (100) MVA and 66/33 kV၊ (30) MVA Kyaiklat Substation since 2014 for more electricity distribution in Ayeyarwaddy Region.Ministry of Electricity and Energy started electric power transmission to Kyaiklat Substation on (28-6-2018) via Hlaingtharya- Kyaiklat Transmission Line and 230/66/11 kV 100 MVA transformer in Kyaiklat Substation.
Kyaiklat Substation’s 66/33 kV၊ (30) MVA Transformer has been transmitted on (29-6-2018) so that Ministry of Electricity and Energy can distribute more electricity to Kyaiklat ၊ Maubin ၊ Pyapon ၊ Dedaye ၊ Bogaleand Mawlamyinegyun Townships and surrounding area on (30-6-2018) from 33 kV feeders of Kyaiklat Substation.