2 January 2019
66 KV Pathein to Ngwesaung transmission line (14.92) miles and 66/11 KV, (5) MVA Ngwesaung substation project was started to construct on 9.2.2016 and then completed on 21.12.2018. So, Ngwesaung and 4817 households of 15 villages near Ngwesaung township are distributed electricity to use in full voltage through National Grid.