66 kV Mawlamyine-Thanbyuzayat power line 40.48 miles, 66/33/11 kV, 20 MVA Thanbyuzayat substation and switchbay extension of Mawlamyine substation construction were started since 2016. These projects were finished on 7-12-2018 and then 12629 households of 28 villages, Thanbyuzayat and Kyaik-kami are distributed with full voltage by 33 kV feeders from 66/33 kV, 20 MVA transformer on 9-12-2018 at 5:00 pm. Current consumption load was 8.5 MW and will manage to supply power to the 21385 households of 95 villages near Mudon and Kamarwatt.