Electricity Supply Enterprise under Ministry of Electricity & Energy, Able Winner Co., Ltd, Soe Moe Than Co., Ltd, Helta Light Co., Ltd and Myanmar Super Ray Co., Ltd sign the Contract for implementation of National Electrification Plan (C1 W1) in Sagaing Division
Electricity Supply Enterprise under Ministry of Electricity & Energy, Able Winner Co., Ltd , Soe Moe Than Co., Ltd , Helta Light Co., Ltd and Myanmar Super Ray Co., Ltd signed the contract for implementation of National Electrification Plan (C1 W1) in Sagaing Division on 21st December, 2018, (14:00) hr at the Meeting Room of MOEE, Office No(27), Nay Pyi Taw. These (4) companies will construct transmission lines and install transformers for getting electricity 482 villages in Sagaing Division.
Read More...
Post under by : Ministry Office
: 21-Dec-2018
Conducting coordination meeting for the projects implementing by Ministry of Electricity and Energy in 2018-2019 Budget Year
The coordination meeting for the projects implementing by MOEE in 2018-2019 Budget Year was held at 09:00 AM, on December 17, 2018 in the meeting room, Office 27.
Union Minister U Win Khaing, Deputy Minister Dr. Tun Naing, Permanent Secretary U Tin Maung Oo, Chairmen from Corporations, Director Generals from Departments, Managing Directors from Enterprises and Divisional Engineers from Regions and States attended this meeting.
Read More...
Post under by : Ministry Office
: 17-Dec-2018
Dr. Tun Naing Deputy Minister for Ministry of Electricity and Energy inspects Electricity and Energy Sectors in Mandalay Region
Dr.Tun Naing, Deputy Minister for Ministry of Electricity and Energy accompanied by responsible persons from Mandalay Electricity Supply Corporation inspected 145 MW Gas Engine Power Plant Project near Belin Substation, Kyauk Se District, Mandalay Region implemented by Powergen Kyaukse Company Limited implementing to supply additional electric power for 2019 summer season on 15th December, 2018.
Read More...
Post under by : Ministry Office
: 15-Dec-2018
Condition in the beginning of power supply from 66 kV Mawlamyine-Thanbyuzayat power line 40.48 miles, 66 kV Thanbyuzayat substation and Switchbay Extension of Mawlamyine substation
66 kV Mawlamyine-Thanbyuzayat power line 40.48 miles, 66/33/11 kV, 20 MVA Thanbyuzayat substation and switchbay extension of Mawlamyine substation construction were started since 2016. These projects were finished on 7-12-2018 and then 12629 households of 28 villages, Thanbyuzayat and Kyaik-kami are distributed with full voltage by 33 kV feeders from 66/33 kV, 20 MVA transformer on 9-12-2018 at 5:00 pm. Current consumption load was 8.5 MW and will manage to supply power to the 21385 households of 95 villages near Mudon and Kamarwatt.
Read More...
Post under by : Department of Power Transmission and System Control (DPTSC)
: 12-Dec-2018
Announcing Ceremony of Natural Gas Master Plan in Myanmar conducted with Technical and Financial Assistance of Economic Research Institute for ASEAN and East Asia - ERIA
- Announcing Ceremony of Natural Gas Master Plan in Myanmar conducted with the Technical and Financial assistance of Economic Research Institute for ASEAN and East Asia (ERIA) joining with Ministry of Electricity and Energy (MOEE) was held at Thingaha Hotel, Nay Pyi Taw on 11-12-2018 at 9:30 am.
Read More...
Post under by : Ministry Office
: 11-Dec-2018