(1) 230kV Mawlamyaing-Myawaddy Line (55.5Miles) and Substation
1. Location
KayinState,Myawaddy and Mon State, Mawlamyaing |
2.Amount of Work
Construction of 230kV Mawlamyaing-Myawaddy Line (55.5Miles)
230 kV Mawlamyaing Substation Switch bay Extension
And 230/66/11kV, (2x50) MVA Myawaddy Substation
3.Situation of Signing Contract
(A) Contract No.(Material) −34, 35, 36, 37, 38 /MEPE(PTP)/ 2014-2015
−14, 15, 16, 22 /MEPE(PTP) /2014-2015
Contractor − Bliss-tel , BME, Alliance,Supplier Global , CCPG,
Power Spectrum
(B) Company Name −Project Manager (Civil) ,Joeyadanar, PyaePhyoKyaw,
(Construction) ChanHein, ChitLinnMyaing, PST,Project Manager (1)
4.Starting Date of Project −1-10-2015
5.Ending Date of Project −March, 2019
(Approximation)
6.Complete Situation −Transmission Line − 100%
− Myawaddy Substation − 100%
− Mawlamyaing Substation − 100%
Switch bay Extension
(23.3.2019)Already Energized the Line & Substation.
(2) 66kV Myawaddy - Myawaddy Line (8.8 Miles) and Substation
1.Location
KayinState,Myawaddy |
2.Amount of Work
66kV Myawaddy – Myawaddy Line (8.8Miles) and
66/11kV, 10MVA Myawaddy Substation
4.Starting Date of Project - 2018
5.Ending Date of Project - April, 2019
(Approximation)
6.Complete Situation - Line - 100%
Substation - 100%
Substation Extension - 100%
(12.4.2019)Already Energized the Line & Substation
(3) 66kV Myawaddy- Kawkareik Line(17.31Miles) and Substation
1. Location
KayinState,Myawaddy and Kawkareik. |
2.Amount of Work
Construction of 66kV Myawaddy- KawkareikLine(17.31Miles)
3.Situation of Signing Contract
(A) Contract No.(Material) −19, 20, 21/MEPE(PTP)/14-15
Contractor −IPL , Zeya , Supplier Global
(B) Company Name −ShweMyitThaungYin, Project Manager (Civil),
(Construction) Project Manager (3)
4.Starting Date of Project −1-10-2015
5.Ending Date of Project −2018- 2019
(Approximation)
6.Complete Situation - Transmission Line − 100%
- Substation − 100%
(26.3.2019)Already Energized the Line & Substation.