1 |
Location |
− |
Bago Township, Bago Region |
2 |
River |
− |
Bago |
3 |
Construction Starting Date |
− |
1.1.1994 |
4 |
Commercial Running Date |
− |
2000 |
5 |
Installed Capacity |
− |
20 MW (2 × 10 MW) |
6 |
Rated Head |
− |
89.9 ft |
7 |
Type of Turbine |
− |
Kaplan (Vertical) |
8 |
Discharge |
− |
2 × 1539 ft3/s = 3078 ft3/s |
9 |
Annual Design Generation |
− |
76 GWh |
10 |
Transmission Line |
− |
66 kV Zaungtu-Kamanat Line (45.6) miles |
11 |
Penstock |
− |
672 ft (2) Nos (f - 16.4 ft) |
1 |
Location |
− |
Kyauktaga Township, Bago Region |
2 |
Creek |
− |
Yenwe |
3 |
Construction Starting Date |
− |
2001 |
4 |
Commercial Running Date |
− |
2007 |
5 |
Installed Capacity |
− |
25 MW (2 × 12.5 MW) |
6 |
Rated Head |
− |
187 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
2 × 883 ft3/s = 1766 ft3/s |
9 |
Annual Design Generation |
− |
123 GWh |
10 |
Transmission Line |
− |
33 kV Yenwe-Thayagone Line 1) & (2) (18.5) miles 11 kV Dam Line (13.5) miles |
11 |
Penstock |
− |
508 ft (f - 18 ft) |
1 |
Location |
− |
Oaktwin Township, Bago Region |
2 |
Creek |
− |
Kabaung |
3 |
Construction Starting Date |
− |
2002-2003 |
4 |
Commercial Running Date |
− |
2008 |
5 |
Installed Capacity |
− |
30 MW (2 × 15 MW) |
6 |
Rated Head |
− |
152 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
2 × 1395 ft3/s = 1766 ft3/s |
9 |
Annual Design Generation |
− |
120 GWh |
10 |
Transmission Line |
− |
33 kV Kabaung-Taung Oo Line (1) & (2) (15) miles |
11 |
Penstock |
− |
210 ft (f - 21 ft) |
Shwegyin
1 |
Location |
− |
Shwegyin Township, Bago Region |
2 |
Creek |
− |
Shwegyin |
3 |
Construction Starting Date |
− |
2002-2003 |
4 |
Commercial Running Date |
− |
2011 |
5 |
Installed Capacity |
− |
75 MW (4 × 18.75 MW) |
6 |
Rated Head |
− |
135.8 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
4 × 1900 ft3/s = 7600 ft3/s |
9 |
Annual Design Generation |
− |
262 GWh |
10 |
Transmission Line |
− |
230 kV Thayagone Line miles (25) miles 11 kV Madauk Line (11) miles |
11 |
Penstock |
− |
1100 ft , (2) Lines (f - 25 ft) |
1 |
Location |
− |
Phyu Township, Bago Region |
2 |
Creek |
− |
Kun |
3 |
Construction Starting Date |
− |
2002-2003 |
4 |
Commercial Running Date |
− |
2012 |
5 |
Installed Capacity |
− |
60 MW (3 × 20 MW) |
6 |
Rated Head |
− |
347 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
3 × 777 ft3/s = 2331 ft3/s |
9 |
Annual Design Generation |
− |
190 GWh |
10 |
Transmission Line |
− |
230 kV Kun-Taungoo Line (37.304) miles 230 kV Kun-Thayagone Line (30.82) miles |
11 |
Penstock |
− |
1295 ft (f - 15 ft) |
1 |
Location |
− |
Taungoo Township, Bago Region |
2 |
Creek |
− |
Thauk Ye Khat |
3 |
Construction Starting Date |
− |
2007-2008 |
4 |
Commercial Running Date |
− |
2013 |
5 |
Installed Capacity |
− |
120 MW (3 × 40 MW) |
6 |
Rated Head |
− |
269 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
3 × 2489.3 ft3/s = 7468 ft3/s |
9 |
Annual Design Generation |
− |
604 GWh |
10 |
Transmission Line |
− |
230 kV Taungoo Line (13.09) miles |
11 |
Penstock |
− |
1972 ft f - 28 ft, (1) No |
1 |
Location |
− |
(7) miles West of Phyu Township, Bago Region |
2 |
Creek |
− |
Phyu |
3 |
Installed Capacity |
− |
40 MW (2 × 20 MW) |
4 |
Rated Head |
− |
337 ft |
5 |
Type of Turbine |
− |
Francis (Vertical) |
6 |
Annual Design Generation |
− |
120 GWh |
1 |
Location |
− |
Shwe Taung Township, Bago Region(Western) |
2 |
Commercial Running Date |
− |
16.2.1982 (Machine -1) 5.6.1982 (Machine-2) 16.4.1984 (Machine -3) |
3 |
Total Installed Capacity |
− |
55.35 MW (3 × 18.45 MW) |
4 |
Type of Machine |
− |
Gas Turbine GE Frame 5 (JOHN BROWN Co., Ltd ) |