1 |
Location |
− |
Bhamaw Township, Kachine State |
2 |
River |
− |
Dapein |
3 |
Construction Starting Date |
− |
2007-2008 |
4 |
Commercial Running Date |
− |
2011 |
5 |
Installed Capacity |
− |
240 MW (4 × 60 MW) |
6 |
Rated Head |
− |
225 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
4 × 3407.75 ft3/s = 13631 ft3/s |
9 |
Annual Design Generation |
− |
1065 GWh |
10 |
Transmission Line |
− |
110 kV Dapein-Bhamaw (23) miles 500 kV Dapein (1) - Daying Jing Stage-4 (1.5) miles |
11 |
Penstock |
− |
1010 ft × (4) Nos (f -16 ft) |
1 |
Location |
− |
Chipwinge Township, Kachine State |
2 |
River |
− |
Chipwi |
3 |
Construction Starting Date |
− |
2013 |
4 |
Commercial Running Date |
− |
5.4.2008 |
5 |
Installed Capacity |
− |
99 MW (3 × 33 MW) |
6 |
Rated Head |
− |
1421 ft |
7 |
Type of Turbine |
− |
Vertical , Pelton |
8 |
Discharge |
− |
311.52 ft3/s |
9 |
Annual Design Generation |
− |
599 GWh |
10 |
Transmission Line |
− |
110 kV (13.09 miles) Chipwinge - Winemaw line |
11 |
Penstock |
− |
8.66 ft × 12.80 ft |