The Work Progress of Minbu Solar Power Project (170 MWAC)
- The 230 kV transmission line (1.3 miles) which connect from Minbu solar project to 230 kV Mann-Ann transmission line has already completed and handed over to Electric Power Generation Enterprise on 12th December 2016.
- The grading work of Phase I (40 MW) has already completed.
- The construction of 11kV (15.5 miles) and 400 V (3 miles) distribution lines has already completed.
- The construction work of Tube well 4 Nos has completed.
- The construction work of Water Ground Tanks and Pump Houses has completed.
- The grading work of Substation (switchyard) has completed.
- MIC permit has already issued since 12th April, 2017.
- The Land Lease Agreement for project area 700 acres has already signed.
- All solar panels for Phase I (40 MW) has transported and uploaded at the project site.
- The ESIA final report has been resubmitted to the Ministry of Natural Resources and Environmental Conservation on 3rd March, 2017.
- GEP (Myanmar) Co., Ltd. is carried out to sign the Land Lease Agreement for the project area 136 acres.