System Improvement


Transmission Lines and Substations under Project

for 2017-2018 Financial Year Union Budget

 

 (1)    Location             

Chin State, Mon State, Shan State (South, North), Sagaing Region, Bago Region(East, West), Magway Region, Ayeyarwaddy Region, Naypyitaw                                   

 

 

 

(b)Project for System Improvement

No

Region/State

Name of Project

1

Mon State

(a)Replacement of  33 kV Mawlamyaing-Mudon and Sittaung-Kyikehto Transmission Lines (22.4 Miles) with Concrete  Poles and Conductors  

 

(b) Upgrading 33/11 kV,5MVA  existing substation to 33/11kV,5MVA substation at  Mudon

2

Shan State (South)

(a) Construction of a 66/33 kV,10 MVA Substation at Kunhein

(b) Upgrading 66/11kV,5MVA existing substation to 66/11kV,20 MVA at Namsang

(c) Upgrading 66/11kV,5MVA existing substation to 66/11kV,10 MVA substation at Loilem

(d) Upgrading 66/11kV,10MVA existing substation to 66/11kV,20 MVA substation at Shwenyaung  

3

Shan State (North)

(a)Construction of 66 kV Mansan-Lashio Transmission Line (29 Miles) and a set of 66kV Switch Bay

(b)Construction of a set of  66kV Switch Bay in Mansan Substation

(c) ) Upgrading 33/11kV,(2 x 5)MVA existing No.2 substation to 33/11kV,(2 x 10 )MVA at Lashio  

4

Sagaing Region

(a)Upgrading 33/11kV existing Shwebo(Thuzar) and Monywar(Industrial

Zone) Substations  

(b)New construction of a  66/11kV,5MVA Kalay (Yarzagyo) substation  (c) Replacement of  33 kV Khinoo-Yeoo and Kyaungkone-Hteechaint Transmission Lines  with Concrete  Poles and Conductors 

(d)Replacement of 33kV No.2 Transmission Line in Monywar( Industrial Zone) substation with Conductor  

(e) Upgrading 33kV single circuit line to 33kV double circuit lines (Aungchanthar substation-Township office substation) in Monywar

5

Bago Region(East)

(a)New construction of 33kV Transmission line from No.2 substation to No.3 substation at Bago

(b)Construction of 33 kV Switch Bays in three 33/11 kV substations at Kanyutkwin,Yeni and Phayargyi    

(c)  Upgrading 33/11kV,5MVA existing substation to 33/11kV,10 MVA substation at Kyauktadar 

6

Bago Region(East)

 Upgrading three 33/11kV,5MVA  existing substations  to 33/11kV,10 MVA substations at Paungte,Nathtaling and Letpatann

7

Magway

(a) ) Upgrading two  33/11kV,5MVA  existing substations  to 33/11kV,10 MVA substations at Pwintphyu and Yenanchaung 

(b) New construction of a 66/11kV,5MVA Substation and 66kV Lines (17.5Miles) in Myohthit(Kangyi),Natmauk Township 

(c)  ) Upgrading  33/11kV,10 MVA  existing substations  to 33/11kV,20 MVA substation in Natmauklann substation at Magway 

(d) ) Upgrading   66/11kV,10 MVA  existing substation  to 66/11kV,20 MVA substation at Taungdwingyi   

8

Ayeyarwaddy Region

(a) ) Upgrading   66/33kV,10 MVA  existing substation  to 66/33kV,     20 MVA Myetto substation at Pathein  

(b) Construction of a set of  66kV extension Switch Bay in Myaungmya Substation

(c) ) Upgrading  33/11kV, 2 MVA  existing substations  to 33/11kV,       5 MVA substation in Daydaye substation at Daydaye  

(d) Construction of a set of  33 kV Switch Bay in 33/11 kV Pantanaw  Substation

(d) Construction of   11kV extension Line (13 Miles) in Pathein (Ngwesaung)

9

Naypyitaw

At Zayyar thiri and Tatkone Townships,

  1. Replacement of 33kV Yesin Transmission  Line in Zayyar Thiri Township with Concrete Poles and  Conductor

 (b) Replacement of 33kV Tatkone-Yamethin Transmission Line in Zayyar Thiri Township with Concrete Poles, Conductor and Insulators

 

(2)Condition of Contract

     Materials of Transmission Lines and Substations have been contracted and bought.

(3)Project Starting Year           −2017

(4) Project Completing Year (Estimated)         −2018

(5)Progress Condition          −   Materials of Transmission Lines and Substations have been contracted and bought by bidding Tender. Final Survey has been accomplished. Projects have been constructed for receiving Transmission Poles. Civil works have being constructed and Installations will be done when the   materials of Substations are received.