Transmission Lines and Substations under Project by Germany KfW (Kreditanstalt fur Wiederaufbau) Loan by Rural Electrification Programme II (Grid Extension) in Southern Shan State
(1)Location
416 villages in Taunggyi, Loilem, Linnkhae Districts, Shan State (South) |
(2) Project Amount
Construction of 66 kV, 33 kV, 11kV Transmission Lines and Substations
(3) Condition of Contract
Funded Sources (Loan) − Germany KfW (Kreditanstalt fur Wiederaufbau)
Contracted Date − 21.9.2017
(4)Project Starting Year −2017
(5) Project Completing Year (Estimated) − (2021-2022)
(6) Progress Condition − Tender is being prepared to bid International Consultant Firm