(1) Still performing the Lines and Substations with JICA Loan (Regional Development Project for Poverty Reduction Phase(MY-P1))
1.Location
Kachin, Kayar, Kayin, Chinn, Mon, Rakhaine, Shan, Mandalay, Sagaing, Magway, Bago, Ayeyarwaddy, Thanintharyi.
2.The amount of Work
Construction of 66kV, 33kV, 11kV,400V Lines and Substations.
3.The Condition of Contract
Loan Agreement No. - Japan ODA Loan (MY-P1)
Organization (Loan) - Regional Development Project for Poverty
Reduction Phase I (MY-P1) JICA Loan
Contract Date - (7.6.2013)
4. Beginning of Project Year - 2014 Yr
5.Ending of Project Year (Forecast) - (2018-2019)
6.Finish Condition - Initial Works have already finished of 100%.
---------------------------------------------------------------------------------------------------------------------------------------
(2) Still performing the Lines and Substations with JICA Loan (Regional Development Project for Poverty Reduction
Phase II (MY-P17))
1.Location
The main townships of Mandalay Division are –
Pyinoolwin, Meiktila, Thazi, Thaungthar, Nyaung Oo, Kyaukpadaung.
2.The amount of Work
Construction of 33kV, 11kV, 400V Lines and Substations.
3.The Condition of Contract
Loan Agreement No - Japan ODA Loan (MY-P17)
Organization (Loan) - Regional Development Project for Poverty
Reduction Phase II (MY-P17)JICA Loan
Contract Date - (1.3.2017)
4.Beginning of Project Year - 2017 Yr
5.Ending of Project Year(Forecast) - (2020-2021)
6.Finish Condition - Consultant Tenders have already been revised.
We are preparing to call working tender now.
---------------------------------------------------------------------------------------------------------------------------------------
(3) Still performing the Lines and Substations with JICA Loan (Power Distribution System Improvement Project in Major Cities in Myanmar (MY-P20))
1.Location
The major cities of Mandalay District are –
Chanayetharsan, Mahaaungmyae, Chanmyatharsi, Pyigyitagon, Amarapura and Patheingyi.
2.The amount of Work
Construction of 33kV, 11kV, 400V Lines and Substations.
3.The Condition of Contract
Loan Agreement No. - Japan ODA Loan (MY-P20)
Organization (Loan) - Power Distribution System Improvement Project in Major Cities in Myanmar (MY-P20) JICA Loan
Contract Date - (1.3.2017)
4.Beginning of Project Year - 2017 Yr
5.Ending of Project Year (Forecast) - (2020-2021)
6.Finish Condition - Consultant Tenders have already been revised.
We are preparing to call working tender now.