1 |
Location |
− |
Thaton Township, Mon State |
2 |
Commercial Running Date |
− |
11.3.1974 (Machine-1 Turbine) 16.9.2010 (Machine-2 Turbine) 15.5.1985 (Machine-3 Turbine) |
3 |
Total Installed Capacity |
− |
50.95 MW |
4 |
Type of Machine |
− |
Hitachi Mark –I MW(JOHN BROWN Mark-II |
5 |
Construction Cost |
|
USD - 2.49 million (Machine –I, II) MMK - 446.5 million (Machine III) |
1 |
Location |
− |
Mawlamyine Township, Mandalay Region |
2 |
Company Name |
− |
Myanmar Lighting (IPP) Co., Ltd |
3 |
Project Type |
− |
BOT |
4 |
Commercial Running Date |
− |
27.5.2014 |
5 |
Total Installed Capacity |
− |
230 MW (95 MW (Phase I) + 130 MW (Phase II) ) |
6 |
Type of Machine |
− |
GE PD 6581B (3 Nos.) LM 2500 (1 No.)GE |
7 |
Annual Design Generation |
− |
1386 GWh |
8 |
Manufacture Company |
− |
GE |
|
|
|
|
Mon State
Sr. |
Name of Transmission Line |
Conductor Size |
Distance (Mile) |
Number of Tower |
State |
1 |
230 kV Thaton - Mawlamyine |
605 MCM |
49.77 |
233 |
Mon State |
Mon State
Sr. |
Name of Transmission Line |
Conductor Size |
Distance (Mile) |
Number of Tower |
1 |
66 kV Mawlamyine - Ngetaw |
397.5 MCM |
1.80 |
39 |
2 |
66 kV Mawlamyine - Chaungsone |
397.5 MCM |
14.86 |
331 |
No |
Substation |
Voltage ratio (kV) |
Capacity (MVA) |
Location |
1 |
Sittaung |
230/33/11 |
50 |
Kyeit-hto Township, Tha-hton District Theinzayat village |
2 |
Mawlamyaine |
230/66/11 |
50 |
Mawlamyaine |
230/66/11 |
50 |
|||
230/66/11 |
50 |
1. 230 kV Sittaung Primary Substation
1. Location
Kyeit-hto Township, Tha-hton District, Mon State
2.Area
(11.24) Acre
3. Commissioning Date
(7-May-2012)
230/33/11 kV 50 MVA (Chint, China)
Total 50 MVA
5. Transmission Lines and Distribution Feeders
(A) 230 kV Transmission Lines
(1) Kamarnat Line
(2) Thaton Line
(B) 33 kV Feeders
(1) Kyeit-hto Feeder
(2) Theinzeik Feeder
(3) Sittaung Paper Factory Feeder
6. Distribution Regions
Kyeit-hto Township and Bee-lin Township
1. Location
No (598-A), Ngan tay Quarters, Mawlamyine District, Mon State
2. Area
(28.53) Acre
3. Commissioning Date
(20-January-2013)
4. Install Capacity
230/66/11 kV 50 MVA (Chint, China)
230/66/11 kV 50 MVA (Chint, China)
230/66/11 kV 50 MVA (Siemens, China)
Total 150 MVA
5. Transmission Lines and Distribution Feeders
(A) 230 kV Transmission Lines
(1) Thaton Line
(2) Myanmar Lighting (IPP) Line
(B) 66 kV Transmission Lines
(1) Industrial Zone+Kha-yone+Pha-yar-gone Line
(2) Mawlamyine Ngan-tay Line
(3) Chaung-sone (1) Line
(4) Mawlamyine Taung substation+ Chaung-sone (2) Line
(5) Mawlamyine (North) Line
6. Distribution Regions
Mawlamyine, Kyitk-mayaw, Mu-done, Than-phyu-zayat, Chaung-sone (Mon State), Pha-yar-gone (Kayin State)
1 |
Location |
− |
Thaton Township, Mon State |
2 |
Commercial Running Date |
− |
11.3.1974 (Machine-1 Turbine) 16.9.2010 (Machine-2 Turbine) 15.5.1985 (Machine-3 Turbine) |
3 |
Total Installed Capacity |
− |
50.95 MW |
4 |
Type of Machine |
− |
Hitachi Mark –I MW(JOHN BROWN Mark-II |
5 |
Construction Cost |
|
USD - 2.49 million (Machine –I, II) MMK - 446.5 million (Machine III) |
1 |
Location |
− |
Mawlamyine Township, Mandalay Region |
2 |
Company Name |
− |
Myanmar Lighting (IPP) Co., Ltd |
3 |
Project Type |
− |
BOT |
4 |
Commercial Running Date |
− |
27.5.2014 |
5 |
Total Installed Capacity |
− |
230 MW (95 MW (Phase I) + 130 MW (Phase II) ) |
6 |
Type of Machine |
− |
GE PD 6581B (3 Nos.) LM 2500 (1 No.)GE |
7 |
Annual Design Generation |
− |
1386 GWh |
8 |
Manufacture Company |
− |
GE |
|
|
|
|
No |
Projects |
Substation |
MVA |
Location |
1 |
66kV Mawlamyaing-Thanbyuzayat line (40.48) miles and substations |
Thanbyuzayat |
66/33kV,20 MVA |
Mon State,Thanbyuzayat. |
1. Location
Mon State,Thanbyuzayat and Mawlamyaing.
2.Amount of Work
Construction of 66kV Mawlamyaing-Thanbyuzayat line (40.48) miles,
66/33kV, 20 MVAThanbyuzayatSubstation and Switch Bay Extension
3.Situation of Signing Contract
Contract No. −40/MEPE(PTP)/15-16
Company Name −KhinMaungNyunt Co., Ltd.
4.Starting Date of Project −9-3-2016
5.Ending Date of Project −2018
(Approximation)
6.Complete Situation − Transmission Line − 100%
− Substation −(100)% (Remained- Test Lab)
- Switch Bay Extension - 100%