1 |
Location |
− |
Yatsauk Township, Shan Sate |
2 |
Creek |
− |
Zawgyi |
3 |
Construction Starting Date |
− |
March 1993 |
4 |
Commercial Running Date |
− |
28th July 1995 |
5 |
Installed Capacity |
− |
18 MW (3 × 6 MW) |
6 |
Rated Head |
− |
383.877 ft (117 m) |
7 |
Type of Turbine |
− |
Francis (Horizontal) |
8 |
Discharge |
− |
3 × 218.73 ft3/s = 656.21 ft3/s |
9 |
Annual Design Generation |
− |
35 GWh |
10 |
Transmission Line |
− |
66 kV Aungthabye Line (50) miles 11 kV Bahtoo Line (11) miles |
11 |
Low Pressure Pipe Line |
− |
902 ft (f - 8 ft) |
12 |
Penstock |
− |
1050 ft (f - 8 ft) |
1 |
Location |
− |
Yatsauk Township, Shan Sate |
2 |
Creek |
− |
Zawgyi |
3 |
Construction Starting Date |
− |
25.9.1995 |
4 |
Commercial Running Date |
− |
1998 |
5 |
Installed Capacity |
− |
12 MW (2 × 6 MW) |
6 |
Rated Head |
− |
106.6 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
2 × 870 ft3/s = 1740 ft3/s |
9 |
Annual Design Generation |
− |
30 GWh |
10 |
Transmission Line |
− |
66 kV Zawgyi (1) Line (17) miles 11 kV Inntaw (8) miles |
11 |
Low Pressure Pipe Line |
− |
105 ft (f - 9.8 ft) |
12 |
Penstock |
− |
320 ft (f - 16.4 ft) |
1 |
Location |
− |
Monage Township, Shan Sate |
2 |
Creek |
− |
Nantein |
3 |
Construction Starting Date |
− |
2003 |
4 |
Commercial Running Date |
− |
2009 |
5 |
Installed Capacity |
− |
54 MW (3 × 18 MW) |
6 |
Rated Head |
− |
427 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
3 × 600 ft3/s = 1800 ft3/s |
9 |
Annual Design Generation |
− |
377.6 GWh |
10 |
Transmission Line |
− |
132 kV Kengtawng-Nansang Line (74) miles 11 kV Kengtawng Line (20) miles |
11 |
Penstock |
− |
2600 ft (f - 15~5 ft) |
Myo Gyi
1 |
Location |
− |
Ywangan Township, Southern Shan Sate |
2 |
Creek |
− |
Zawgyi |
3 |
Construction Starting Date |
− |
2005-2006 |
4 |
Commercial Running Date |
− |
2016 |
5 |
Installed Capacity |
− |
30 MW (2 × 15 MW) |
6 |
Rated Head |
− |
171.9 ft (52.4 m) |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
1836 ft3/ Sec |
9 |
Annual Design Generation |
− |
135.70 GWh |
10 |
Transmission Line |
− |
33 kV (10.g niles). Double Circuit To Taung Taw Kwin Substation |
Shweli No. (1)
1 |
Location |
− |
Nam Hkan Township, Shan Sate |
2 |
River |
− |
Shweli |
3 |
Construction Starting Date |
− |
2002-2003 |
4 |
Commercial Running Date |
− |
2009 |
5 |
Installed Capacity |
− |
600 MW (6 × 100 MW) |
6 |
Rated Head |
− |
981 ft |
7 |
Type of Turbine |
− |
Francis (Vertical) |
8 |
Discharge |
− |
6 × 1328.7 = 7972.2 ft3/s |
9 |
Annual Design Generation |
− |
4022 GWh |
10 |
Transmission Line |
− |
230 kV Shweli-Mansan-To Taung Taw Kwin Substation Shwesaryan Line (1) & (2) (180) miles |
11 |
Low/ High Pressure Pipe Line |
- |
3030 ft × (2) Nos (f -17 ft) |
Tigyit
1 |
Location |
− |
Pin Laung Township, Shan State |
2 |
Company Name |
− |
Wuxi Huaguang Electric Power Engineering Co.,Ltd |
3 |
Project Type |
− |
RBOT |
|
Construction Starting Date |
− |
2001 |
4 |
Commercial Running Date |
− |
24.12.2004 (Machine –I ) 3.5.2005 (Machine-II) |
5 |
Total Installed Capacity |
− |
120 MW (2 × 60 MW) |
6 |
Type of Machine |
− |
Coal-fired Thermal Power Turbine and Generator |
7 |
Annual Design Generation |
− |
600 GWh |
8 |
Transmission Line |
− |
132 kV Tigyit-Lawpita Line (1) & (2) (76.614) miles 132 kV Tigyit-Kalaw Line (1) & (2) (22) miles |
Shan State
Sr. |
Name of Transmission Line |
Conductor Size |
Distance (Mile) |
Number of Tower |
State/Division |
1 |
230 kV Shweli - Mansan |
605 MCM |
59.60 |
323 |
Shan State |
2 |
230 kV Mansan - Shwesaryan |
605MCM |
120.60 |
634 |
Shan State |
Shan State
Sr. |
Name of Transmission Line |
Conductor Size |
Distance (Mile) |
Number of Tower |
1 |
132 kV Ba Lu Chaung (2) - Tigit |
397.5 MCM |
83.84 |
404 |
2 |
132 kV Tigit - Kalaw |
397.5 MCM |
17.49 |
80 |
3 |
132 kV Kyaungtaung - Nansan |
397.5 MCM |
73.88 |
395 |
4 |
132 kVNansan - Pinpet |
397.5 MCM |
43.13 |
193 |
5 |
132 kV Kalaw – Pinpet (1) |
397.5 MCM |
40.02 |
178 |
6 |
132 kV Pinpet – Kalaw (2) |
397.5 MCM |
39.86 |
182 |
7 |
132 kV Taunggyi Substation In/Out |
397.5 MCM |
0.85 |
5 |
Shan State
Sr. |
Name of Transmission Line |
Conductor Size |
Distance (Mile) |
Number of Tower |
1 |
66 kV Kalaw - Aungthapyay |
304.6 MCM |
31.56 |
505 |
2 |
66 kV Nansan - Loilin |
397.5 MCM |
14.00 |
183 |
3 |
66 kV Mansan - Hsipaw |
397.5 MCM |
23.10 |
331 |
4 |
66 kV Mansan - Lashio |
397.5 MCM |
26.00 |
413 |
5 |
66 kV Shweli (1) – Nantkhan - Muse |
397.5 MCM |
39.31 |
510 |
6 |
66 kV Nansan - Moenal |
397.5 MCM |
30.90 |
528 |
7 |
66 kV Moenal - Linkhay |
397.5 MCM |
17.10 |
282 |
8 |
66 kV Nansan - Kholan |
397.5 MCM |
27.61 |
424 |
9 |
66 kV Panlone - Nansan |
397.5 MCM |
18.12 |
91 |
10 |
66 kV Kholan - Wansin |
397.5 MCM |
20.00 |
338 |
11 |
66 kV Wansin - Minenaung |
397.5 MCM |
22.54 |
385 |
12 |
66 kV Aungthapyay - Naungkar |
397.5 MCM |
16.93 |
238 |
13 |
66 kV Kalaw - Pintaya |
397.5 MCM |
21.73 |
306 |
14 |
66 kV Loilin - Laechar |
397.5 MCM |
27.31 |
429 |
15 |
66 kV Laechar - Minekaing |
397.5 MCM |
27.50 |
438 |
16 |
66 kV Lashio - Mineyal |
397.5 MCM |
48.18 |
809 |
17 |
66 kV Lashio - Theinni |
185 sqmm |
34.00 |
555 |
18 |
66 kV Kholan - Kunhein |
397.5 MCM |
32.66 |
412 |
19 |
66 kV Theinni - Tamoenyae |
397.5 MCM |
23.10 |
383 |
20 |
66 kV Mineyal - Tantyang |
397.5 MCM |
32.50 |
393 |
21 |
66 kV Zawgyi(1)-Aungthapyay |
185 sqmm |
47.47 |
651 |
22 |
66 kV Zawgyi(1)- Zawgyi(2) |
185 sqmm |
14.02 |
223 |
No |
Substation |
Voltage ratio (kV) |
Capacity (MVA) |
Location |
1 |
Mansan |
230/66/11 |
60 |
Kyaukmae Distinct, Namatu Township, Mansam Village
|
No |
Substation |
Voltage ratio (kV) |
Capacity (MVA) |
Location |
1 |
Kalaw |
132/66 |
80 |
Kalaw Township, Innpyin village |
|
|
132/33/11 |
50 |
|
2 |
Nansan |
132/66/11 |
60 |
Nansan |
3 |
Taunggyi |
132/66/11 |
50 |
Taunggyi |
132/66/11 |
50 |
1. Location
Nantmatu Township, Kyauk-mae District, Shan (North) State
2. Area
(70) Acre
3. Commissioning Date
(7-July-2008)
4. Install Capacity
230/66/11 kV 60 MVA (LEEEC, China)
Total 60 MVA
5. Transmission Lines and Distribution Feeders
(A) 230 kV Transmission Lines
(1) Shwesaryan (1) Line
(2) Shwesaryan (2) Line
(3) Shweli (1) Line
(4) Shweli (2) Line
(B) 66 kV Transmission Lines
(1) Thi-baw Line
(2) Lasho Line
(3) Mansan Line
6. Distribution Regions
Lasho Township, Kuit-khaing Township, Tant-yan Township, Mine-yael Township, Kyauk-mae Township, Thi-baw Township, Nant-matu Township and Nant-san Township
1. 132 kV Kalaw Primary Substation
1. Location
Inn-pyin Village, Kalaw Township, Taunggyi District, Southern Shan State
2. Area
(15.83) Acre
3. Commissioning Date
(2-September-1992)
4. Installed Capacity
132/33/11 kV, 50 MVA (Chint, China)
132/66 kV, 80 MVA (Paulwels Trafo, Belgium)
Total 130 MVA
5. Transmission Lines and Distribution Feeders
(A) 132 kV Transmission Lines
(1) Tigit (1) Line
(2) Tigit (2) Line
(3) Taunggyi (1) Line
(4) Taunggyi (2) Line
(5) Yepaungsone (1) Line
(6) Yepaungsone (2) Line
(B) 66 kV Transmission Lines
(1) Aungthapya Line
(2) Dragon Cement Factory Line
(3) Pin-ta-ya Line
(C) 33 kV Distribution Feeders
(1) Naung-tayar Feeder
(D) 11 kV Distribution Feeders
(1) Kalaw Feeder
(2) Aung-pann Feeder
(3) Military Feeder
6. Distribution Regions
Kalaw Township, Aungban Township, Pin-ta-ya Township, Ywar-ngan, Yart-suat, Hae-ho , Taung-gyi, Shwe Nyaung, Nyaung Shwe, Aye-thar-yar, Te-gyit, Naung-ta-yar, Pin-laung, Ho-pone
1. Location
Nansan Township, Loi-lem District, Southern Shan State
2. Area
(34.4) Acre
3. Commissioning Date
(26-July-2008)
4. Installed Capacity
132/66/11 kV, 60 MVA (Xian, China)
Total 60 MVA
5. Transmission Lines and Distribution Feeders
(A) 132 kV Transmission Lines
(1) Kyaing-taung Line
(2) (Nansan)-Pinpet Line
(B) 66 kV Transmission Lines
(1) Loi-lem Line
(2) Nansan Line
(3) Moe-neh Line
(4) Kho-lam Line
6. Distribution Regions
Loi-lem District, Lin-khay District
1. Location
Kangyi Quarters, Taunggyi District, Southern Shan State
2. Area
(42) Acre
3. Commissioning Date
(30-April-2017)
4. Installed Capacity
132/66/11 kV, 50 MVA (Xian XD, China)
132/66/11 kV, 50 MVA (Xian XD, China)
Total 100 MVA
5. Transmission Lines and Distribution Feeders
(A) 132 kV Transmission Lines
(1) Kalaw (1) Line
(2) Kalaw (2) Line
(3) Nansan Line
(4) Pinpet Line
(B) 66 kV Distribution Feeders
(1) Aung-thapyae Feeder
(2) Substation (3) Feeder
6. Distribution Regions
Aye-thar-yar Industrial Zone, Kan-bawza Cement Factory, Se-sai, Naung-mon, Naung-talan, Hotel Zone, Sikekhauk, Taunggyi Substation, Downtown (8) Quarters in Taunggyi Township